TRACO-CCV line (dry cure technology) for the manufacture of UG and AB cables of voltage range 11/33/66 KV at Thiruvalla unit of Traco Cable Company Ltd
  • Project Start Date

    2021-11-01

  • Project Cost

    1600.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-11-01

  • Physical Progress

    66.2 %

  • .

KCCL-Supercapacitor Production Facility
  • Project Start Date

    2021-01-13

  • Project Cost

    1800.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2022-12-13

  • Physical Progress

    57.75 %

  • .

SIFL- Modernization Project
  • Project Start Date

    2021-09-06

  • Project Cost

    1782.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2024-03-21

  • Physical Progress

    81.25 %

  • .

SILK- 3. Installation of Machines in SILK Foundry Unit, Ottapalam
  • Project Start Date

    2021-06-26

  • Project Cost

    570.71 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-12-26

  • Physical Progress

    99.5 %

  • .

KSIE-Modernization of Container Freight Station (CFS)
  • Project Start Date

    2021-10-01

  • Project Cost

    300.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2024-03-31

  • Physical Progress

    96.67 %

  • .

KSIE-KERALA SOAPS-Setting up of Plant and Machinery for manufacturing of Liquid Hand wash Soaps in Kerala Soaps
  • Project Start Date

    2021-09-30

  • Project Cost

    250.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2024-03-31

  • Physical Progress

    98.0 %

  • .

KECL-Development and Production of Vibration Isolator for Industrial Applications
  • Project Start Date

    2022-01-01

  • Project Cost

    50.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2023-03-31

  • Physical Progress

    66.67 %

  • .

FIT - INSTALLATION OF HORIZONTAL BANDSAW MACHINE
  • Project Start Date

    2022-02-02

  • Project Cost

    60.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-08-02

  • Physical Progress

    66.67 %

  • .

UEIL-Manufacture of Polymer Insulator
  • Project Start Date

    2021-09-15

  • Project Cost

    216.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-07-15

  • Physical Progress

    100.0 %

  • .

KELTRON-Manufacturing Medical Equipment, Augmentation of SPG
  • Project Start Date

    2021-07-01

  • Project Cost

    463.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-03-31

  • Physical Progress

    71.18 %

  • .

SIFL - Expansion of Shoranur Machining Unit
  • Project Start Date

    2021-12-20

  • Project Cost

    565.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-11-19

  • Physical Progress

    100.0 %

  • .

KMML-Compact and Energy Efficient Tickle Pre-heaters
  • Project Start Date

    2023-03-22

  • Project Cost

    2150.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2025-03-20

  • Physical Progress

    0.0 %

  • .

KMML- Liquid Nitrogen Storage
  • Project Start Date

    2020-05-26

  • Project Cost

    495.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-05-26

  • Physical Progress

    100.0 %

  • .

KMML- Addiitonal cooling tower
  • Project Start Date

    2020-10-18

  • Project Cost

    950.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-06-21

  • Physical Progress

    95.94 %

  • .

KMML-New Brine Chilling Compressor System
  • Project Start Date

    2020-12-11

  • Project Cost

    300.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-08-11

  • Physical Progress

    98.33 %

  • .

LVP/SVP AND OPHTHALMIC PLANT COMPLETION OF PROJECT
  • Project Start Date

    2019-10-30

  • Project Cost

    5887.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    73.5 %

  • .

KELTRON-Modernization of Production facilities AS Revalidated
  • Project Start Date

    2019-07-01

  • Project Cost

    535.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    69.69 %

  • .

TTPL- Modernisation projects- Copperas Recovery Plant
  • Project Start Date

    2018-03-31

  • Project Cost

    1550.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2021-03-31

  • Physical Progress

    96.94 %

  • .

SILK- 4. Installation of Machines in SILK GEW Unit, Thuravoor
  • Project Start Date

    2021-06-26

  • Project Cost

    129.29 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-12-26

  • Physical Progress

    87.0 %

  • .

SILK- 2. Drydocking Slipway at SILK Azhikkal Unit
  • Project Start Date

    2020-06-15

  • Project Cost

    450.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-11-15

  • Physical Progress

    95.71 %

  • .

SILK- 1. Modernisation of SILK SFU Unit, Cherthala
  • Project Start Date

    2020-06-15

  • Project Cost

    300.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2021-12-15

  • Physical Progress

    100.0 %

  • .

MALABAR CEMENTS LIMITED -Bulk Cement Terminal & Allied Material Handling and Logistics Hub at Cochin Port trust (CPT)
  • Project Start Date

    2022-02-15

  • Project Cost

    16655.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-02-15

  • Physical Progress

    33.33 %

  • .

INTEGRATED COCONUT AND FRUIT PROCESSING COMPLEX
  • Project Start Date

    2019-05-15

  • Project Cost

    650.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-05-15

  • Physical Progress

    100.0 %

  • .

KCCP-FUEL RETAIL OUTLETS
  • Project Start Date

    2022-03-01

  • Project Cost

    280.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-11-01

  • Physical Progress

    25.0 %

  • .

Modernisation
  • Project Start Date

    2022-03-15

  • Project Cost

    250.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-15

  • Physical Progress

    100.0 %

  • .

PRELIMINARY WORKS IN ONCOLOGY PARK
  • Project Start Date

    2021-01-11

  • Project Cost

    300.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-12-31

  • Physical Progress

    85.0 %

  • .

KSDP-NON BETALACTAM PROJECT
  • Project Start Date

    2017-08-10

  • Project Cost

    3794.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-12-31

  • Physical Progress

    98.0 %

  • .

HDCK-Karakausala Sauhrida Padhathi
  • Project Start Date

    2021-10-30

  • Project Cost

    300.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2022-03-30

  • Physical Progress

    100.0 %

  • .

KMML- 5 TPH Pressure Filtration and Drying System
  • Project Start Date

    2021-06-05

  • Project Cost

    9000.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-10-05

  • Physical Progress

    73.86 %

  • .

TCSM-NCDC Assisted Rehabilitation cum Modernisation and Expansion programme of Trichur Co-operative Spinning Mills ltd
  • Project Start Date

    2015-03-27

  • Project Cost

    2997.78 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-06-27

  • Physical Progress

    93.42 %

  • .

KSTC - Value addition through installation of Autoconer at Prabhuram Mills
  • Project Start Date

    2022-02-14

  • Project Cost

    395.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-02-14

  • Physical Progress

    13.06 %

  • .

KSTC-Value addition in Malabar Spiniing & Weaving Mills, Kozhikode
  • Project Start Date

    2022-02-14

  • Project Cost

    599.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-02-14

  • Physical Progress

    58.67 %

  • .

KSTC-Komalapuram Spinning & Weaving Mills, Alappuzha
  • Project Start Date

    2022-02-03

  • Project Cost

    273.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    91.33 %

  • .

KSTC-Hi-tech Weaving Mills, Pinarayi
  • Project Start Date

    2022-03-15

  • Project Cost

    108.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-15

  • Physical Progress

    9.93 %

  • .

KSTC- Uduma Textile Mills, Kasargode
  • Project Start Date

    2022-02-03

  • Project Cost

    140.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    100.0 %

  • .

KSTC-Modernization of CARDT
  • Project Start Date

    2022-03-15

  • Project Cost

    415.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-15

  • Physical Progress

    0.0 %

  • .

KAL-Expansion and Modernisation of facilities for manufacturing E-Auto, E-Rickshaw & E-Scooter
  • Project Start Date

    2021-11-15

  • Project Cost

    816.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-11-15

  • Physical Progress

    74.71 %

  • .

KAL-New factory at Pinarayi, Kannur for assembling of electric vehicles manufactured by Kerala Automobiles Ltd
  • Project Start Date

    2021-09-30

  • Project Cost

    350.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-09-30

  • Physical Progress

    20.45 %

  • .

KKMCSM-Modernization
  • Project Start Date

    2022-03-01

  • Project Cost

    100.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-03-31

  • Physical Progress

    0.0 %

  • .

SIDCO-MODERNIZATION OF 8 PRODUCTION UNITS OF SIDCO
  • Project Start Date

    2021-07-09

  • Project Cost

    249.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-03-31

  • Physical Progress

    100.0 %

  • .

TRAVANCORE CEMENTS LTD- 400TPD GREY CEMENT GRINDING UNIT
  • Project Start Date

    2022-01-10

  • Project Cost

    957.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2024-01-10

  • Physical Progress

    22.57 %

  • .

TRAVANCORE CEMENTS LTD.- POLE CASTING UNIT
  • Project Start Date

    2022-11-01

  • Project Cost

    591.85 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2024-05-01

  • Physical Progress

    66.67 %

  • .

KCCL - Expansion and Modernization of Capacitor Production Facility
  • Project Start Date

    2021-06-03

  • Project Cost

    300.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    85.11 %

  • .

MIL-Installation of 3T Hammer and other modernisation works
  • Project Start Date

    2020-08-15

  • Project Cost

    492.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-12-15

  • Physical Progress

    49.71 %

  • .

MIL-Setting up of Regional Depots/Show rooms
  • Project Start Date

    2022-05-16

  • Project Cost

    100.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-11-15

  • Physical Progress

    44.0 %

  • .

AKL- INSTALLATION OF 2MW SOLAR POWER PLANT IN THE PREMISES OF AUTOKAST LTD
  • Project Start Date

    2020-08-28

  • Project Cost

    1033.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2023-06-21

  • Physical Progress

    70.36 %

  • .

kaithari Suraksha Scheme
  • Project Start Date

    2022-01-20

  • Project Cost

    110.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-03-31

  • Physical Progress

    100.0 %

  • .

RENOVATION OF INDUSTRIAL ESTATE SIDCO
  • Project Start Date

    2021-02-17

  • Project Cost

    501.0 lakhs

  • Category

    Construction

  • Project End Date

    2021-08-30

  • Physical Progress

    100.0 %

  • .

TELK-VAPOUR PHASE DRYING SYSTEM
  • Project Start Date

    2022-05-30

  • Project Cost

    1100.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-05-30

  • Physical Progress

    0.0 %

  • .

TKCL- PRODUCTION CAPACITY STABILIZATION - 1500MT PER MONTH
  • Project Start Date

    2021-10-01

  • Project Cost

    700.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    80.71 %

  • .

KEL - MODERNISATION & EXPANSION OF KUNDARA & MAMALA UNITS
  • Project Start Date

    2017-08-03

  • Project Cost

    1800.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-12-03

  • Physical Progress

    77.8 %

  • .

Bamboo-'Production of Bamboo Based Green Protocol Office Equipment'
  • Project Start Date

    2021-06-27

  • Project Cost

    250.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2022-06-27

  • Physical Progress

    0.0 %

  • .

ECO FRIENDLY BRICK MANUFACTURING FROM MOULDING SAND WASTE
  • Project Start Date

    2021-09-24

  • Project Cost

    56.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-05-08

  • Physical Progress

    91.25 %

  • .

AUTOKAST-MODERNISATION PROJECT
  • Project Start Date

    2021-03-01

  • Project Cost

    1134.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-06-30

  • Physical Progress

    16.17 %

  • .

MODENIZATION AND EXPANSION OF PLANT AND MACHINERY
  • Project Start Date

    2020-12-26

  • Project Cost

    600.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2024-03-26

  • Physical Progress

    80.22 %

  • .

Comprehensive Revival Scheme of Co-Operative Spinning Mills (Under TEXFED)- Alleppey Co-Operative Spinning Mills Ltd
  • Project Start Date

    2022-02-04

  • Project Cost

    230.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-02-04

  • Physical Progress

    42.86 %

  • .

CCSM - COMPLETION OF CURRENT NCDC ASSISTED MORDERNISATION PROGRAMME
  • Project Start Date

    2021-04-01

  • Project Cost

    1750.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-31

  • Physical Progress

    97.91 %

  • .

MALCOTEX-Mordernisation of Malcotex
  • Project Start Date

    2021-11-01

  • Project Cost

    150.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-01-01

  • Physical Progress

    100.0 %

  • .

Rejuvenation and Revival of Viable PSUs - Fund Support to PRICO for Modernization
  • Project Start Date

    2022-01-13

  • Project Cost

    115.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-04-13

  • Physical Progress

    100.0 %

  • .

MCSM-Comprehensive Revival Scheme for Cooperative Spinning mills
  • Project Start Date

    2021-08-27

  • Project Cost

    175.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2023-01-30

  • Physical Progress

    100.0 %

  • .

NCDC Comprehensive Revival Scheme for Co-operative Spinning Mills - QCSM Ltd
  • Project Start Date

    2021-09-09

  • Project Cost

    500.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2022-03-31

  • Physical Progress

    100.0 %

  • .

KEL - MANUFACTURE OF ELECTRIC VEHICLE MOTORS AT KUNDARA UNIT
  • Project Start Date

    2020-07-15

  • Project Cost

    1000.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-04-30

  • Physical Progress

    37.54 %

  • .

KSTC- Technology upgradation in Edarikkode Textiles
  • Project Start Date

    2022-03-03

  • Project Cost

    372.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2023-03-03

  • Physical Progress

    12.5 %

  • .

Desiltation of Meenkara DAM on Turn Key basis
  • Project Start Date

    2022-01-19

  • Project Cost

    7461.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2023-01-19

  • Physical Progress

    66.67 %

  • .

TTPL- Modernization of Titanium Dioxide plant, Neutralization Plant
  • Project Start Date

    2022-04-01

  • Project Cost

    16838.0 lakhs

  • Category

    Modernization of PSUs

  • Project End Date

    2026-04-01

  • Physical Progress

    60.1 %

  • .

Dredging and Beach Sand Mining at Palakkod,Valiyakadappuram
  • Project Start Date

    2020-03-21

  • Project Cost

    968.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2022-08-31

  • Physical Progress

    87.24 %

  • .

Desiltation of Walayar DAM on Turn Key basis
  • Project Start Date

    2021-10-01

  • Project Cost

    7213.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2024-10-01

  • Physical Progress

    70.0 %

  • .

SETTING UPOF ONCOLOGY PARK
  • Project Start Date

    2022-03-01

  • Project Cost

    15000.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2025-03-01

  • Physical Progress

    0.0 %

  • .

TTPL- New Diversified Projects - Manufacture of Red ,Yellow and Black Oxide from ferrous sulphate solution
  • Project Start Date

    2022-08-01

  • Project Cost

    13061.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2025-08-30

  • Physical Progress

    5.99 %

  • .

TTPL- New Diversified Projects - Manufacturing of Plaster of Paris from White Gypsum
  • Project Start Date

    2022-07-23

  • Project Cost

    5478.36 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2025-08-30

  • Physical Progress

    7.69 %

  • .

TTPL- New Diversified Projects- Manufacture of Catalytic Titanium Dioxide, Coloured Pigments, Lithium Titanate and Pearl pigment from Titanium Dioxide.
  • Project Start Date

    2022-08-02

  • Project Cost

    5261.68 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2025-08-30

  • Physical Progress

    6.25 %

  • .