Board for Public Sector Transformation
Project wise achievements
TRACO-CCV line (dry cure technology) for the manufacture of UG and AB cables of voltage range 11/33/66 KV at Thiruvalla unit of Traco Cable Company Ltd
-
Project Start Date
2021-11-01
-
Project Cost
1600.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2023-11-01
-
Physical Progress
66.2 %
-
.
UEIL-UPGRADATION OF MOTOR STARTER
-
Project Start Date
2021-09-15
-
Project Cost
61.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2022-04-20
-
Physical Progress
100.0 %
-
.

KMML-Compact and Energy Efficient Tickle Pre-heaters
-
Project Start Date
2023-03-22
-
Project Cost
2150.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2025-03-20
-
Physical Progress
0.0 %
-
.
KMML- Liquid Nitrogen Storage
-
Project Start Date
2020-05-26
-
Project Cost
495.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2022-05-26
-
Physical Progress
100.0 %
-
.
Modernisation
-
Project Start Date
2022-03-15
-
Project Cost
250.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-15
-
Physical Progress
100.0 %
-
.
KSTC - Value addition through installation of Autoconer at Prabhuram Mills
-
Project Start Date
2022-02-14
-
Project Cost
395.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-02-14
-
Physical Progress
13.06 %
-
.
KSTC-Value addition in Malabar Spiniing & Weaving Mills, Kozhikode
-
Project Start Date
2022-02-14
-
Project Cost
599.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-02-14
-
Physical Progress
58.67 %
-
.
KSTC-Komalapuram Spinning & Weaving Mills, Alappuzha
-
Project Start Date
2022-02-03
-
Project Cost
273.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-31
-
Physical Progress
91.33 %
-
.
KSTC-Hi-tech Weaving Mills, Pinarayi
-
Project Start Date
2022-03-15
-
Project Cost
108.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-15
-
Physical Progress
9.93 %
-
.
KSTC- Uduma Textile Mills, Kasargode
-
Project Start Date
2022-02-03
-
Project Cost
140.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-31
-
Physical Progress
100.0 %
-
.
KSTC-Modernization of CARDT
-
Project Start Date
2022-03-15
-
Project Cost
415.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-15
-
Physical Progress
0.0 %
-
.
KAL-New factory at Pinarayi, Kannur for assembling of electric vehicles manufactured by Kerala Automobiles Ltd
-
Project Start Date
2021-09-30
-
Project Cost
350.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2023-09-30
-
Physical Progress
20.45 %
-
.
KKMCSM-Modernization
-
Project Start Date
2022-03-01
-
Project Cost
100.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2022-03-31
-
Physical Progress
0.0 %
-
.
TRAVANCORE CEMENTS LTD- 400TPD GREY CEMENT GRINDING UNIT
-
Project Start Date
2022-01-10
-
Project Cost
957.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2024-01-10
-
Physical Progress
22.57 %
-
.
TRAVANCORE CEMENTS LTD.- POLE CASTING UNIT
-
Project Start Date
2022-11-01
-
Project Cost
591.85 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2024-05-01
-
Physical Progress
66.67 %
-
.
kaithari Suraksha Scheme
-
Project Start Date
2022-01-20
-
Project Cost
110.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2022-03-31
-
Physical Progress
100.0 %
-
.
TELK-VAPOUR PHASE DRYING SYSTEM
-
Project Start Date
2022-05-30
-
Project Cost
1100.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-05-30
-
Physical Progress
0.0 %
-
.
Bamboo-'Production of Bamboo Based Green Protocol Office Equipment'
-
Project Start Date
2021-06-27
-
Project Cost
250.0 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2022-06-27
-
Physical Progress
0.0 %
-
.
AUTOKAST-MODERNISATION PROJECT
-
Project Start Date
2021-03-01
-
Project Cost
1134.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-06-30
-
Physical Progress
16.17 %
-
.
Comprehensive Revival Scheme of Co-Operative Spinning Mills (Under TEXFED)- Alleppey Co-Operative Spinning Mills Ltd
-
Project Start Date
2022-02-04
-
Project Cost
230.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-02-04
-
Physical Progress
42.86 %
-
.
NCDC Comprehensive Revival Scheme for Co-operative Spinning Mills - QCSM Ltd
-
Project Start Date
2021-09-09
-
Project Cost
500.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2022-03-31
-
Physical Progress
100.0 %
-
.
KSTC- Technology upgradation in Edarikkode Textiles
-
Project Start Date
2022-03-03
-
Project Cost
372.0 lakhs
-
Category
Modernization of PSUs
-
Project End Date
2023-03-03
-
Physical Progress
12.5 %
-
.
SETTING UPOF ONCOLOGY PARK
-
Project Start Date
2022-03-01
-
Project Cost
15000.0 lakhs
-
Category
Mega Projects
-
Project End Date
2025-03-01
-
Physical Progress
0.0 %
-
.
TTPL- New Diversified Projects- Manufacture of Catalytic Titanium Dioxide, Coloured Pigments, Lithium Titanate and Pearl pigment from Titanium Dioxide.
-
Project Start Date
2022-08-02
-
Project Cost
5261.68 lakhs
-
Category
Expansion/Diversification of PSUs
-
Project End Date
2025-08-30
-
Physical Progress
6.82 %
-
.