Directorate of Coir Development

Project wise achievements

Manufacturing and distribution of ASM to Coir co-operative societies
  • Project Start Date

    2021-08-05

  • Project Cost

    947.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2022-08-05

  • Physical Progress

    100.0 %

  • .

Manufacture and distribution of electronic ratts
  • Project Start Date

    2019-02-27

  • Project Cost

    950.0 lakhs

  • Category

    Mega Projects

  • Project End Date

    2020-02-27

  • Physical Progress

    100.0 %

  • .

Installation of Solar panels and its associated units in coir co-operatives in Kerala
  • Project Start Date

    2020-06-11

  • Project Cost

    32.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2021-06-11

  • Physical Progress

    100.0 %

  • .

Mattress Stitching and finishing unit
  • Project Start Date

    2022-06-01

  • Project Cost

    182.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-06-30

  • Physical Progress

    40.0 %

  • .

Upgradation of Coir Composite Board unit at Kanichukulangara
  • Project Start Date

    2022-06-01

  • Project Cost

    210.0 lakhs

  • Category

    Expansion/Diversification of PSUs

  • Project End Date

    2023-06-30

  • Physical Progress

    8.33 %

  • .