KSIDC
Project wise achievements
Purchase of land from KSIE for setting up regional office of KSIDC at Kozhikode
-
Project Start Date
2022-02-15
-
Project Cost
500.0 lakhs
-
Category
Land Acquisition
-
Project End Date
2022-03-15
-
Physical Progress
0.0 %
-
.
Construction of business incubation cum office complex building at Kakkanad
-
Project Start Date
2022-02-01
-
Project Cost
3529.0 lakhs
-
Category
Construction
-
Project End Date
2026-03-31
-
Physical Progress
0.0 %
-
.
KSIDC-Angamaly Land
-
Project Start Date
2022-04-01
-
Project Cost
0.0 lakhs
-
Category
Land Allotment
-
Project End Date
2023-06-30
-
Physical Progress
100.0 %
-
.
Industrial Growth Centre Kannur
-
Project Start Date
2022-04-01
-
Project Cost
0.0 lakhs
-
Category
Land Allotment
-
Project End Date
2023-03-31
-
Physical Progress
24.0 %
-
.
Industrial Growth Centre Kozhikode
-
Project Start Date
2022-04-01
-
Project Cost
0.0 lakhs
-
Category
Land Allotment
-
Project End Date
2023-03-31
-
Physical Progress
40.0 %
-
.
KSIDC-Light Engineering Industrial Park(LEIP)-Palakkad
-
Project Start Date
2008-04-28
-
Project Cost
4459.0 lakhs
-
Category
Land Allotment
-
Project End Date
2023-03-31
-
Physical Progress
100.0 %
-
.
KSIDC Industrial Growth Centre,Pallipuram Cherthala
-
Project Start Date
2000-01-01
-
Project Cost
0.0 lakhs
-
Category
Land Allotment
-
Project End Date
2023-03-31
-
Physical Progress
98.0 %
-
.
LEIP Palakkad -drawing 22 KV dedicated feeder line from Walayar Substation
-
Project Start Date
2022-04-30
-
Project Cost
107.8 lakhs
-
Category
Construction
-
Project End Date
2023-12-31
-
Physical Progress
66.67 %
-
.
Phase 2 Part Development of land at IGC Kannur
-
Project Start Date
2022-04-01
-
Project Cost
1458.0 lakhs
-
Category
Construction
-
Project End Date
2024-03-31
-
Physical Progress
45.83 %
-
.
Construction of SDF building at KSIDC Industrial Space (KIS) Kasargod
-
Project Start Date
2022-05-11
-
Project Cost
3970.0 lakhs
-
Category
Construction
-
Project End Date
2025-12-31
-
Physical Progress
33.33 %
-
.
Study on utilization of land and masterplan preparation for Kuttiyadi Park
-
Project Start Date
2022-03-28
-
Project Cost
34.0 lakhs
-
Category
Land Allotment
-
Project End Date
2022-06-28
-
Physical Progress
0.0 %
-
.
M/s Dhathri Ayurveda Pvt. Ltd. - Facility for manufacture of ayurvedic extracts, nutraceuticals, therapeutic and prophylactic drugs, and R&D facility
-
Project Start Date
2021-08-15
-
Project Cost
4700.0 lakhs
-
Category
Fisheries
-
Project End Date
2025-08-15
-
Physical Progress
33.33 %
-
.
M/s Azcco Global Ventures - Biscuit Manufacturing (Craze brand) unit in IGC Kozhikode
-
Project Start Date
2021-10-01
-
Project Cost
4000.0 lakhs
-
Category
Fisheries
-
Project End Date
2025-10-01
-
Physical Progress
60.0 %
-
.
M/s Plant Lipids Pvt. Ltd. - Capacity expansion of spices extraction facility in Kochi
-
Project Start Date
2021-10-08
-
Project Cost
20000.0 lakhs
-
Category
Fisheries
-
Project End Date
2025-10-08
-
Physical Progress
100.0 %
-
.
M/s Builtech Foundation - Construction of Commercial Building in Palakkad
-
Project Start Date
2021-10-11
-
Project Cost
30000.0 lakhs
-
Category
Fisheries
-
Project End Date
2025-10-11
-
Physical Progress
100.0 %
-
.
M/s GEEKOM (M/s Avigna Pvt. Ltd.) - Industrial & Logistics Park and Warehouse in Ernakulam
-
Project Start Date
2022-01-24
-
Project Cost
50000.0 lakhs
-
Category
Fisheries
-
Project End Date
2023-01-24
-
Physical Progress
50.0 %
-
.
M/s Muralya Dairy Products Pvt. Ltd. - Diary Processing Plant and Logistics Unit in Ernakulam
-
Project Start Date
2022-03-31
-
Project Cost
7000.0 lakhs
-
Category
Fisheries
-
Project End Date
2024-03-31
-
Physical Progress
100.0 %
-
.
M/s H-Pack Packaging Industries Pvt. Ltd. - Manufacturing facility for Disposable Food Packaging in Ernakulam
-
Project Start Date
2022-06-01
-
Project Cost
10000.0 lakhs
-
Category
Fisheries
-
Project End Date
2023-12-20
-
Physical Progress
95.0 %
-
.
Dedicated water Supply line by KWA to IGC, Kannur - laying of 2 Kms pipeline from KWA pump house to OH tank
-
Project Start Date
2022-03-28
-
Project Cost
282.0 lakhs
-
Category
Construction
-
Project End Date
2024-03-31
-
Physical Progress
60.0 %
-
.